Project Timeline
| Month | Description |
|---|---|
| January | University Procurement requests bids for electronic routing system |
| February | Selected vendors visit campus for Sandbox sessions with University staff and faculty |
| March | Kuali Research selected as vendor for new electronic routing system |
| April | RSP staff begins meeting with Kuali staff to begin implementation process |
| May |
- PIFs no longer routed via BizFlow; paper process begins for summer months - RSP staff continues meeting with Kuali staff to begin implementation process |
| June |
- New electronic routing system named “GrantLaunch” - RSP staff continues meeting with Kuali staff to begin implementation process |
| July | Kuali on-site visit for GrantLaunch training with RSP staff |
| August | Initial GrantLaunch training with University fiscal analysts and Deans |
| September |
- GrantLaunch training sessions with faculty and department chairs - Full implemention of GrantLaunch begins; paper routing of PIFs ends |